The quickest boost for most organizations' bottom line is
finding opportunities for decreasing costs without sacrificing quality. An area
frequently overlooked is the inventory of parts kept for maintenance, repair,
and operations (MRO).
Typically, managers hesitate to initiate a cost-cutting
project in this area because they fear that critical parts may not be available
when they are needed. And the number of parts that can be reduced-typically one
or two-may seem too few to yield meaningful cost savings.
In fact, however, it is possible to minimize the capital
invested in inventory without risking equipment and production downtime or
disruption caused by cyclical preventive maintenance. To achieve this goal,
managers must:
- Isolate the sources of demand for MRO parts.
- Improve the processes for creating an inventory for planned requirements.
- Improve safety stock calculation.
- Improve the processes for unplanned requirements.
- Optimize parts ordering.
Step 1: Isolate the Sources of Demand
Two primary types of demand drive MRO parts inventory:
- Planned requirements, which include:
- Parts used during scheduled maintenance, cleanup, or quality inspection
processes. Most of these items are consumable, and requirements for them are
predictable over time.
- Replacement parts for which need can be predicted by equipment age and mean
time between failure (MTBF) data as provided by the manufacturer.
- Unplanned requirements, which result from unanticipated equipment failure or
accidents.
Step 2: Improve Processes for Planned Requirements
Typical inventories for planned replacement parts can be
minimized through:
- Rigorous adherence to inventory control processes.
- Accurate inventory quantity data.
- Accurate purchasing lead-time data.
- Accurate MTBF data.
- Predictable scheduled maintenance cycles.
- Accurate parts requirements lists for preventive maintenance work orders.
- Inventory system flexibility to order upgrade replacement parts in a timely
manner through the formal system.
Many if not all of these processes already are in place in
most companies that hold moderate to large parts inventories. But they
frequently are not a high priority for rigorous administration, and they rarely
are optimized. Thus, considerable opportunities exist for improvements that
readily result in cost savings.
Experience shows that emphasizing these processes can result
in significant initial reductions in MRO parts inventories; additional
reductions almost always follow as staff confidence and expertise in the
processes increase.
Step 3: Improve Safety Stock Calculation
Recommending purchase orders to replenish stocked parts is a
key function of an effective computerized maintenance management system (CMMS)
or Enterprise Asset Management (EAM) program, which aims to minimize total
equipment downtime. But while these programs trigger reorders when safety stocks
sink below specified levels, they depend on manual input to determine what those
safety stock levels should be.
Calculating the safety stock quantity involves multiple
variables, such as:
- Verification that the supported equipment is still in service.
- Cost of the part.
- Shortest delivery time from all sources, including off-site storage,
supplier distribution points, and sister facilities.
- MTBF and standard deviation for the part.
- Criticalness of equipment the part supports.
- Availability of substitute parts or work-around processes.
In practice, systematic inclusion of these variables in the
calculation is rare. Safety stock levels frequently are determined by
maintenance engineers or information technology support staff using
seat-of-the-pants or cover-every-instance estimates that exceed quantities
actually needed.
Safety stock can be further optimized when staff have access
to data and algorithms that can help them balance inventory costs against the
risk of corporate loss. Developing such algorithms requires a clear
understanding of the company's long- and short-term financial goals.
Step 4: Improve Processes for Unplanned Requirements
MRO inventories frequently contain major components of
mission-critical equipment-an extra engine is common. These components
frequently are purchased at the same time as the equipment and capitalized as
part of the total purchase. All too often multisite facilities duplicate these
rarely needed components and retain them until the equipment is retired,
resulting in the need to discard essentially new components.
Comparing component stockpiles available at different sites
and reducing component inventories as equipment nears its replacement date can
minimize such expenditures.
Companies can realize cost savings when their sites compare
and share this inventory. To maximize multisite sharing, staff must adhere
rigorously to a common system of describing parts so that searches of multisite
inventories return correct results quickly.
Increasingly effective preventive
maintenance programs reduce the demand for unplanned MRO parts inventories.
Reality dictates, however, that the demand for such parts never falls to zero.
Step 5: Optimize Ordering
Ideally, each part would be ordered when the projected demand
generated from a future scheduled maintenance work order exceeds the quantity on
hand, minus safety stock. The purchase order due date is calculated as
follows:
- Begin with the date required for scheduled preventive maintenance.
- Back up this date by the time required for internal picking and kitting of
the material for the maintenance work order.
- Back up this new date by internal receiving, inspection, and testing time.
- Back up this new date by delivery time from the vendor site or distribution
point to the receiving dock.
- Back up this new date by accurate (neither inflated nor rush) supplier
lead-time.
- Back up the new date by some factor for safety time (if required based on
supplier and transportation reliability).
- Back up the new date by internal purchase order processing and approval
lead-time.
Cost-cutting opportunities in this area include
- Reducing minimum order requirements negotiated with the supplier.
- Introducing supply chain initiatives such as vendor consolidation and
electronic ordering. These frequently are already in place for large purchase
orders. Extending them to the small order quantities characteristic of MRO often
is cost-effective.
- Eliminating safety time used to ensure timely delivery of parts. Safety time
(not to be confused with safety stock) can frequently be reduced or eliminated
as supplier programs and supplier communications evolve.
Opportunity Knocks More Than Once
An inflated MRO inventory is an opportunity for cost
reductions in most manufacturing organizations. And bringing it under control is
not a one-time event. For instance, MRO inventory must be re-evaluated
periodically to ensure that it is reduced appropriately following:
- Mergers with or acquisitions of companies with similar or identical
equipment. Mergers also create the potential for stocks to be consolidated and
reduced if the same MRO parts support multiple pieces of equipment.
- Changes in technology. Newly available parts from either the original
manufacturer or an aftermarket supplier may, for instance, extend MTBF.
- Changes in corporate strategy that alter the importance of specific
equipment and its products to the bottom line. Such changes may significantly
alter the risk factors used to optimize the capital investment in parts.